Conversion vs New Build

Garage Conversion to ADU: Costs, Permits and When It Pays Off

Floor plan of the Four Fifty studio ADU

Converting a garage into an ADU in California typically costs $80,000 to $168,000 and takes 5 to 9 months including permit time. That sounds cheap compared to a $309K new ADU, but the math is often not as good as it looks on paper. Many garage conversions end up at the higher end of the range once you account for code-required upgrades, foundation reinforcement, utility runs and finish quality.

The honest decision framework: convert your garage if the existing structure is structurally sound, in good repair, and you don’t need garage parking. Build a new factory-built ADU instead if the garage has any structural questions, you’d lose needed parking, or you want a home that performs and feels like new construction.

The short version: Garage conversion = $80K to $168K typical, 5 to 9 months. New factory-built ADU = $199K to $599K all-inclusive with a permitting budget included, about 4 to 9 months depending on the model (4 months is best case for our smallest home, and permitting adds time), with new framing and insulation throughout. Conversion wins on price; a new build wins on space, layout and a home built new from the foundation up.

On this page

What “garage conversion” actually involves

A code-compliant garage conversion in California requires every one of these:

  1. Foundation upgrade. Existing garage slabs are typically thin (3.5”) and unreinforced. For habitable conversion, you’ll often need to demo or reinforce the slab, especially in seismic zones.
  2. Wall and roof insulation. Garages have R-0 walls. You’ll insulate to current Title 24 standards (R-21 walls, R-30 to R-38 roof). Often requires furring out walls and adding new wall framing.
  3. Window and door replacement. Garage doors get replaced with a real entry door + windows for code-required egress and natural light.
  4. Plumbing. A new kitchen and bath means new water supply, drain lines, and a separate sewer connection (or branch from the main house).
  5. Electrical. A new electrical panel or expanded service. Existing garage circuits are usually not enough for a kitchen + HVAC + bath.
  6. HVAC. New heating and (in many regions) cooling. Usually a mini-split heat pump.
  7. Drywall, paint, flooring, cabinetry, appliances, fixtures. Full interior buildout.
  8. Code compliance for fire, sound, energy. Updated to current 2026 California Building Code + Title 24.

Each of these has a real cost. Add them up honestly and a “$60K garage conversion” turns into $120K once you’re done, sometimes more. For a side-by-side look at lower-cost paths, see the cheapest way to build an ADU.

Where the costs actually land

Realistic cost ranges by phase for a typical 400 sq ft California garage:

Homes being framed inside the Framework First factory in Salinas
Homes take shape indoors at our Salinas factory.
PhaseTypical cost
Permits, plans, Title 24$4,000 to $10,000
Foundation reinforcement / slab work$8,000 to $25,000
Framing modifications (walls, doors, windows)$10,000 to $20,000
Insulation + drywall$8,000 to $15,000
Plumbing (kitchen + bath)$12,000 to $25,000
Electrical + HVAC$10,000 to $18,000
Kitchen + cabinets + countertops + appliances$15,000 to $30,000
Bath fixtures + finishes$8,000 to $15,000
Flooring + paint + finish work$5,000 to $10,000
Total range$80,000 to $168,000

The high end of the range applies to: detached garages requiring new utility runs, garages with structural issues (rotted sill plates, foundation cracks), high-cost-of-labor markets (San Francisco, San Jose proper), and finishes that match a new-build quality.

Permits for a garage conversion

California state ADU law treats garage conversions as ADUs, meaning they get the same protections (60-day ministerial review, no owner-occupancy requirement, and no replacement parking for the garage you convert).

What that means in practice:

  • Cities can’t reject the conversion for being an ADU.
  • They CAN require it to meet current building code (insulation, egress, fire protection).
  • The 60-day clock starts when you submit a complete application.
  • You don’t need to replace the parking the garage held. State law bars cities from requiring it for a garage converted to an ADU.

The “parking replacement” question is the one homeowners most often get wrong. California cities used to be able to require you to replace any parking you lost in a garage conversion. State law now bars cities from requiring replacement parking when a garage, carport or covered parking structure is converted to an ADU or torn down to build one. Our ADU parking requirements guide covers the rest of the parking rules.

Realistic timeline

A garage conversion typically runs:

  • Permits: 60 to 90 days (the state’s 60-day rule applies; complex permits take longer)
  • Foundation + framing modifications: 4 to 8 weeks
  • Mechanicals (plumbing/electrical/HVAC): 3 to 5 weeks
  • Insulation + drywall: 2 to 3 weeks
  • Finishes (cabinets, appliances, paint, flooring): 4 to 6 weeks
  • Inspections + punchlist: 2 to 4 weeks

Total: 5 to 9 months from permit submission to certificate of occupancy. That’s in the same range as a new factory-built ADU, but with all the work happening at your property, not off-site.

The honest comparison: convert vs build new

FactorGarage conversionNew factory-built ADU (Framework First Six Sixty 1BR)
Cost$80K to $168K$309K, permitting budget included*
Build time5 to 9 months5 months
All work happens on your propertyYes (disruption to daily life)No (about 97% built off-site, then set by crane)
FoundationReinforced existing slabNew foundation poured on your property for the home
Wall framing2x4 wall (after furring)2x6 exterior walls
InsulationAdded to existing walls to meet Title 24Installed in the factory, Title 24 compliant
Square footage flexibilityLimited to garage footprint (~200 to 500 sq ft)405 to 1,200 sq ft, your choice
Layout flexibilityGarage shape constrains floor planDesigned-for-purpose floor plan
Resale appeal”Converted garage” framing”Detached ADU” framing
Selections locked inOften time and materials with allowancesYour model price, add-ons and any promotion are held for you

*Includes a permitting budget, not final permit costs. Permits and property-specific site work (septic, retaining walls, etc.) vary by property and are confirmed in your feasibility study.

When garage conversion is genuinely the right call

We don’t build garage conversions (we build new factory-built ADUs). But here’s our honest take on when a conversion makes more sense:

  1. Budget below $150K hard-cap. Even our cheapest model is $199K. If $150K is your absolute ceiling, conversion is the only path forward.
  2. The existing garage is structurally excellent. Recent construction (2000+), no settling, no water issues, no rotted framing.
  3. You don’t need the garage for parking. State law means you won’t have to replace those spaces, but make sure the rest of the lot still parks your household.
  4. You’re okay with a smaller home. Garages cap out around 400 to 500 sq ft. If you want anything bigger, you’d be building an addition AND converting, which loses the price advantage fast. If you’re weighing building on top of the garage instead, our garage ADU guide covers that route and the height rules that come with it.
  5. You’re handy and willing to general-contractor the project yourself. Owner-managed conversions can cost less than hiring a full GC.

When a new factory-built ADU is the better call

  1. You want a new home, not a converted space. A conversion is shaped by the walls, slab and roof you already have. A new ADU is designed as a home from the start.
  2. You want more room. Our models run from 405 to 1,200 square feet, so you can pick the size and bedroom count instead of living inside the garage’s footprint.
  3. You want to rent it out. A one- or two-bedroom home with its own designed layout is a different rental than a converted single room. Rents vary by city, and our guide to how much rent an ADU can earn walks through how to estimate yours.
  4. You want a clearer budget. A Framework First home is all-inclusive with a permitting budget built in, and your model price, add-ons and any promotion are held for you. Conversions often run on allowances, and hidden conditions in an older structure can add cost.
  5. You need the garage for your own cars. The city can’t make you replace the spaces, but you lose them.

What we’d actually recommend

When homeowners ask us “should I convert the garage or build a new ADU?”, the answer depends on the garage, the budget and how you plan to use the space. A new ADU gives you more room, a layout built for living and most of the construction happening in our factory instead of your driveway.

For tight budgets, structurally sound garages and owners who don’t need the parking and want the lowest-cost path to a rentable studio, a conversion can be the right call. We’d recommend hiring a licensed CA contractor who specializes in ADU conversions specifically, not a general remodeler.

If you want to compare the two for your property, start with a feasibility study. It confirms what a new ADU on your lot would involve, so you can weigh it against a conversion quote side by side. If a conversion turns out to be the better fit for you, that’s the honest call.


Comparing your options? Take the 30-second yard-fit quiz to see which Framework First model fits your lot, or run the ROI calculator to compare the financial scenarios.

Next Step · Factory Tour

Walk through finished homes at our Salinas factory →

See homes being built indoors and meet a member of our team.

Form not loading? Open it directly →

Talk to a Real Person

Have a question this didn't answer?

Tell us a bit about your property below, and one of our Account Managers will follow up with a straight answer, not a form letter. Or call (831) 432-7721 directly.

  • A shortlist of which models actually fit your lot
  • Honest flags on anything property-specific, like slope or septic
  • A clear next step, whether that is a factory tour or a feasibility study
  • No pressure, and no obligation

Building more than one? If you're a real estate developer or investor planning multiple units, let us know in the form. We offer better pricing at volume.

“My first telephone conversation with Cathy (Owner) was one of the best, positive and kind discussions. She was thinking outside of the box and provided a possible solution like a family member. Thank you.”

Vijay Kumar

on Google

See If My Property QualifiesFree property analysis
Start