ADU Process · 2026

How Long Does It Take to Build a 1,000 Sq Ft ADU?

Plan on about 6 to 9 months from contract for a 1,000 square foot prefab ADU, subject to local permitting, which is the part no builder controls. Our 945 square foot homes take about 6 months and our 1,200 square foot homes 7 to 9 months, because the factory builds the home while the site work happens. A fully site-built ADU of the same size often takes a year or more.

The short version: The timeline has three parts: design and permits, the build, and delivery and finish. State law requires cities to decide on a complete ADU application within 60 days, but real-world reviews often take longer because of correction rounds, utility sign-offs or a coastal permit. Building the home in a factory while the foundation goes in is what keeps the total short.

On this page

A typical timeline for a 1,000 square foot prefab ADU

StageWhat happensTypical length
Feasibility and designSite check, model and layout chosen, plans finalized2 to 6 weeks
PermitsPlan check, corrections, utility and fire sign-offs, coastal permit if neededAbout 2 to 4 months, depending on your city
Factory buildThe home is built indoors, about 97% completeRuns at the same time as site work
Site workFoundation, utility trenching, sewer or septic workRuns at the same time as the factory build
Delivery and setTrucked in and set by craneUsually one day
Finish and finalHookups, finish work and final inspectionA few weeks

Our model timelines, from contract and subject to local permitting:

ModelSizeTypical timeline
Nine Forty-Five (2 and 3 bedroom versions)945 sq ftAbout 6 months
Twelve Hundred1,200 sq ft7 to 9 months
Twelve Hundred U1,200 sq ft7 to 9 months

What California law says about permit timing

Under Government Code section 66317, the city has 15 business days to tell you whether your application is complete, and 60 days to approve or deny a complete application. If it denies, it must give you a written list of what to fix, and you can appeal. In the coastal zone, the coastal permit also runs on a 60-day clock, at the same time as the ADU review. Asking the city to pause the review stops the clock.

Homes being framed inside the Framework First factory in Salinas
Homes take shape indoors at our Salinas factory.

Real reviews often run longer than 60 days in total because each correction round restarts part of the work. Complete, accurate plans are the best way to stay close to the legal timeline.

What slows a 1,000 square foot ADU down

  • Incomplete plans and correction rounds.
  • Coastal permits in parts of Monterey and Santa Cruz counties.
  • Utility and fire sign-offs, including sewer capacity or a new electric meter.
  • Septic or well approvals on rural parcels.
  • Grading, soils or a sloped lot that needs engineering.
  • Historic districts or HOA review.

Why prefab is faster for a 1,000 square foot ADU

On a site-built project, framing can’t start until the foundation is done, and every trade works in sequence, outdoors. With a factory-built home, the house is built indoors while the foundation goes in, then arrives about 97% complete and is set by crane in a day. A bigger home adds more to the factory schedule than to your site schedule.

Does size change the timeline much?

Less than people expect. Size changes the price more than the schedule. Our smallest homes run about 4 to 5 months in the best case and our largest 7 to 9 months, all subject to local permitting.

Frequently asked questions

How long does it take to build a 1,000 sq ft ADU?

About 6 to 9 months from contract for a prefab ADU, subject to local permitting. A site-built ADU of the same size often takes a year or more.

How long do ADU permits take in California?

The city has 15 business days to confirm your application is complete and 60 days to approve or deny a complete one. In practice, correction rounds, utility sign-offs and coastal permits can make the total longer.

Is a 1,000 sq ft ADU allowed in California?

Yes. Every city’s maximum must allow at least 1,000 square feet for an ADU with more than one bedroom, and the state default for a detached ADU is 1,200 square feet. See how big can an ADU be in California.

Does a two-story ADU take longer?

Usually, because of more structural engineering and review. Note that California guarantees a minimum height for detached ADUs (16 feet, more near transit), so a two-story detached ADU depends on your city’s rules.

What is the fastest way to get an ADU built?

Start with a feasibility study, submit complete plans, and choose a factory-built home so the build and the site work happen at the same time.

Your next step

  1. See the full step-by-step process in how long does it take to build an ADU.
  2. Read the permit rules in ADU permit timeline in California.
  3. Book a free Online Property Analysis on our contact page, and we’ll talk through a realistic timeline for your lot.

Next Step · Factory Tour

Walk through finished homes at our Salinas factory →

See homes being built indoors and meet a member of our team.

Form not loading? Open it directly →

Talk to a Real Person

Have a question this didn't answer?

Tell us a bit about your property below, and one of our Account Managers will follow up with a straight answer, not a form letter. Or call (831) 432-7721 directly.

  • A shortlist of models worth exploring for your goals
  • Honest flags on anything property-specific, like slope or septic
  • A clear next step, whether that is a factory tour or a feasibility study
  • No pressure, and no obligation

Building more than one? If you're a real estate developer or investor planning multiple units, let us know in the form. We offer better pricing at volume.

“My first telephone conversation with Cathy (Owner) was one of the best, positive and kind discussions. She was thinking outside of the box and provided a possible solution like a family member. Thank you.”

Vijay

on Google

Book my property analysisFree and online, about 30 minutes
Start