Timeline & Process

How Long Does It Take to Build an ADU in California? (2026)

A home being built inside the Framework First factory in Salinas

Building an ADU in California takes about 4 to 9 months with a Framework First factory-built home, depending on the model, and commonly 16 to 24 months for a site-built ADU. Our Four Fifty studio is the best case at about 4 months. Permitting is the one step no builder fully controls, so every timeline depends on your city’s review.

Every other model up to the Nine Forty-Five takes about 5 to 6 months, and the 1,200 square foot homes take 7 to 9, counted from the day your construction deposit lands rather than the day you sign. State law gives your city 60 days to approve or deny a complete ADU application when there is already a home on the lot, and how quickly your application gets there sets the final pace.

The short version: About six to seven weeks of planning (property analysis, factory tour, feasibility study, design). Then, once financing is in place, a build stage of about 4 to 9 months where your home is built in our factory during permit review, and the foundation goes in once the city issues your permit, with permit timing set by your city. One crane day, finish work and the final inspection close it out.

On this page

ADU timeline, stage by stage

Here is how a Framework First ADU comes together on a typical project. Your feasibility study turns these ranges into dates for your parcel.

StageTypical timeWhat happens
The ADU Designer by Framework FirstAnytime, on your scheduleDesign and price a home online, no sign-up needed
Online Property Analysis (OPA)Week 1, a free 30-minute callWe confirm your lot can host an ADU and which models fit
Factory tourWeek 1, about 90 minutesWalk finished homes in our Salinas factory with a member of our team
Site visit + feasibility studyWeeks 2 to 4, about a week longer for an empty lotCrane access, utilities and placement checked in person; the study takes 14 business days ($497), or 21 for an empty lot ($997)
Review findings + finalize your designWeeks 5 to 6Walk through the study, finalize your selections in The ADU Designer, sign
Permits60-day state clock once the application is completeWe prepare and submit plans; the city checks completeness, then approves or denies
Factory buildStarts during permit reviewAbout 97% of the home is built indoors in our Salinas factory
Foundation + utility stub-outsOnce your permit is issuedOur crew prepares your lot while the home is finished in the factory
Crane deliveryOne dayThe home is trucked over, set on the foundation by crane, and the first hookups are made
Finish work + final inspectionAfter delivery dayFinal connections and details, the city’s final inspection, then your Certificate of Occupancy

Weeks 1 to 6 move as fast as your decisions do. The build clock runs about 4 to 9 months depending on the model, from the day your construction deposit lands to final inspection, once your financing is in place. The $1,000 signup deposit you place when you sign reserves your spot; it does not start permitting or material orders. See the full 7-step process for what each stage involves.

How long each Framework First model takes

ModelSizeBed / bathEstimated build time
Four Fifty450 sq ftStudio / 1About 4 months, best case
The 405405 sq ft1 / 1About 5 months
Five Five Five555 sq ft1 / 1About 5 months
Six Sixty660 sq ft1 / 1About 5 months
Six Sixty Duo660 sq ft2 / 1About 5 months
Seven Forty-Nine749 sq ft2 / 1About 5 to 6 months
Eight Eighty-Five Duo885 sq ft2 / 1About 6 months
Eight Eighty-Five Duo Plus885 sq ft2 / 2About 6 months
Nine Forty-Five Duo945 sq ft2 / 1About 6 months
Nine Forty-Five Duo Plus945 sq ft2 / 2About 6 months
Nine Forty-Five Trio945 sq ft3 / 1About 6 months
Nine Forty-Five Trio Plus945 sq ft3 / 2About 6 months
Twelve Hundred1,200 sq ft3 / 2About 7 to 9 months
Twelve Hundred U1,200 sq ft3 / 2About 7 to 9 months

Build times run from the day your construction deposit lands to final inspection. They are estimates, and permit timing is set by your city, so your feasibility study confirms the schedule for your lot.

Why a factory-built ADU is faster

Site-built construction is linear: the permit comes first, then every trade works one after another on your property. Our homes run on two tracks at once.

  • The home and the paperwork move together. Your home is built in our Salinas factory while the city reviews your permit, and once the permit is issued our crew prepares your lot while the home is finished. Our guide to ADU site preparation covers what happens in your yard during that stretch.
  • Weather stays outside. Framing, wiring, plumbing and finishes happen indoors, so the rainy season does not pause the factory build.
  • Proven models. Our crews build the same models again and again, so there is no figuring it out on site.
  • One delivery day. The finished home is trucked to your lot and set by crane in a single day. Here is how ADU crane delivery works.

How permits fit into your ADU timeline

California sets the outer limits. According to the California Department of Housing and Community Development’s ADU Handbook (March 2026 edition), state law (Government Code section 66317) requires the permitting agency to:

  • Confirm completeness within 15 business days. The city must tell you in writing whether the application is complete and, if not, list what is missing. If it misses that deadline, the application is deemed complete.
  • Approve or deny within 60 days of a complete application when there is already a home on the lot. Review is ministerial, checked against objective standards without a hearing.
  • Explain any denial in full. A denial must come with every reviewer’s comments and how to fix them, and a resubmitted application starts a new 60-day period.

Two more rules from the handbook matter for your calendar. If you ask the city for a delay, the 60-day clock pauses for that time. And before anyone moves in, the ADU needs a Certificate of Occupancy from the local agency.

In practice, completeness decides how long permitting takes. A clean first submission keeps you on one 60-day clock, and a denial and resubmittal starts another. That is why we prepare plans the way each local department expects them. Our California ADU permit timeline guide goes deeper.

How long ADU permits take in your city

The state clock is the same everywhere, but each permit counter has its own workload and local rules. Our local guides walk through the timeline week by week:

We also cover Aptos, Carmel, Gilroy, Los Altos, Los Gatos, Marina, Morgan Hill and Watsonville, plus Santa Clara County and unincorporated Monterey County and Santa Cruz County.

What slows an ADU down

  • An incomplete application. The 60-day clock only starts once the package is complete, and a denial and resubmittal starts it over.
  • Coastal review. Parcels inside the mapped Coastal Zone usually need coastal review as well, either a coastal development permit or an exclusion or exemption. When there is already a home on the lot, state law has a coastal development permit decided alongside the ADU permit, within 60 days of a complete application, but the extra documentation adds prep time. See building an ADU in a coastal zone.
  • Septic. If your home is on septic rather than sewer, the county typically reviews whether the system can handle an ADU, and an upgrade adds design and construction time. Read our ADU septic guide.
  • Utility upgrades. A new electrical service or sewer connection can add time on the utility’s schedule. Here is how ADU utility hookups work.
  • Tight site access. Narrow side yards, trees or overhead lines can change the crane plan, which is why we confirm access at the site visit.
  • Financing. The build clock starts with your construction deposit, so closing your loan comes first. Our guide to financing an ADU in California lays out the options.
  • Home size. The 1,200 square foot homes take 7 to 9 months because there is simply more house to build.

How much each of these affects your project varies by parcel, and your feasibility study confirms it for your lot before you sign. For what that study includes, see what an ADU feasibility study is.

Factory-built vs. site-built ADU timeline

Framework First factory-builtTypical site-built
Total timeAbout 4 to 9 months by model, with permit timing set by your cityCommonly 16 to 24 months
Permits and constructionOverlap: the home is built during permit reviewOne after the other: construction starts after the permit
WeatherAbout 97% built indoorsFraming and trades exposed on site
Construction in your yardSite prep and foundation, one crane day, then finish workMost of the project

Site-built ADUs take longer because design, permits and construction happen in sequence, with weather and subcontractor scheduling in between. Our prefab vs. site-built ADU comparison covers the other tradeoffs.

The fastest path to move-in

  • Choose a proven model. The Four Fifty is the 4-month best case, and The 405, Five Five Five, Six Sixty and Six Sixty Duo run about 5 months, with permit timing set by your city.
  • Settle your design early. Start in The ADU Designer so your layout and finishes are ready when your study comes back.
  • Talk to your lender early. Financing comes before the build clock starts.
  • Book your feasibility study early. Septic, coastal or utility questions surface before your design is final, not after.

Frequently asked questions

How long does it take to build an ADU in California?

About 4 to 9 months with a Framework First factory-built home, depending on the model, and commonly 16 to 24 months for a site-built ADU. State law gives your city 60 days to approve or deny a complete ADU application when there is already a home on the lot, and permit timing is the one part no builder fully controls.

How long does it typically take to build an ADU?

For most of our homes, The 405 through the Nine Forty-Five models (everything except the Four Fifty and the 1,200 square foot homes), about 5 to 6 months from the day your construction deposit lands to final inspection. Plan on about six weeks before that for the property analysis, factory tour, feasibility study and design. Your city’s permit timing can move either number.

What is the fastest an ADU can be built?

Our Four Fifty studio is the best case at about 4 months from the day your construction deposit lands to final inspection, with clean permitting. Because permitting is the step nobody fully controls, we treat 4 months as a best case, not a promise.

How do permits affect the ADU timeline?

In California, the city must tell you within 15 business days whether your application is complete, then approve or deny a complete application within 60 days when there is already a home on the lot. If an application is denied and resubmitted, a new 60-day period starts, so a complete first submission is the fastest path. We prepare and submit the plans for you.

Which step takes the longest?

The build stage, about 4 to 9 months depending on the model, where the factory build runs during permit review and the foundation follows once the permit is issued. Within it, permitting is the least predictable part, which is why the factory build runs alongside it instead of waiting for it.

How long does crane delivery take?

One day. The finished home is trucked from our Salinas factory, set onto the foundation by crane, and the first utility hookups happen the same day. Finish work and the city’s final inspection follow before move-in.

How much longer does a site-built ADU take?

A site-built ADU commonly takes 16 to 24 months, compared with about 4 to 9 months for a Framework First home by model, subject to your city’s permit timing. The difference is sequencing: a site build waits for the permit and then stacks every trade on your lot, while our homes are built in the factory during permit review.


Want a timeline for your address? Book a free Online Property Analysis and our team will map the steps, the model options and the permit path for your lot. Or start designing now in The ADU Designer.

Next Step · Factory Tour

Walk through finished homes at our Salinas factory →

See homes being built indoors and meet a member of our team.

Form not loading? Open it directly →

Talk to a Real Person

Have a question this didn't answer?

Tell us a bit about your property below, and one of our Account Managers will follow up with a straight answer, not a form letter. Or call (831) 432-7721 directly.

  • A shortlist of which models actually fit your lot
  • Honest flags on anything property-specific, like slope or septic
  • A clear next step, whether that is a factory tour or a feasibility study
  • No pressure, and no obligation

Building more than one? If you're a real estate developer or investor planning multiple units, let us know in the form. We offer better pricing at volume.